Project Review
Project Review
A project
review is conducted to determine the causes of cost or time overruns, excessive
change orders, contractors claims, or other issues which lead to
unsatisfactory results in construction projects. This information may also
prove helpful in structuring projects from the outset. Listed below are the
five areas which Big Sky reviews.
- Was a
project budget established?
- Was it
available to all team members?
- Was the
project contingency amount adequate for change order needs?
- Were A/E
estimates done for each stage of design?
- Were A/E
estimates reviewed for budget compatibility?
- If there
were issues of budget non-compliance, were measures taken to achieve
compliance?
- Was the
owner aware of the budget status?
Project Schedules Checklist
- Was a
master schedule developed for the construction program?
- Was a
project schedule developed for each project?By Whom?
- Were
monthly schedule updates received?
- Was the
project schedule reviewed and updated? How Often?
- Was the
project on schedule? If not, What actions were taken to correct?
- Was the
schedule status documented on a monthly basis? Were comments returned to
the contractor on the updated schedule submittal?
- Were
progress payments integrated with the schedule?
- Were time
extension requests analyzed against the project schedules?
- How many
delay days were requested? How many were granted?
- Were
short-interval schedules submitted by the contractors?
Contract Administration Checklist
- Were
frequent job site meetings held?
- Were
minutes taken and published?
- Were
procedures for handling incoming and outgoing correspondence, logging,
filing and distribution established and followed?
- Were
submittals/substitutions logged and tracked?
- How were
substitutions identified and dealt with?
- Was a
procedure for review of RFI's established?
- Were
responses to contractors timely?
- Were RFIs
logged and tracked?
- What
actions were taken on delayed RFIs?
- Were
reports on project status produced an distributed regularly?
- Was the
frequency and format of reporting to owner, in any format, adequate?
- What kind
of information was forwarded to the owner?
- What level
of decision was deferred to the owner?
Change Orders Checklist
- How were
change orders generated?
- How were
contractor's requests for change orders tracked?
- How was
the cost of the change order determined?
- Was an
independent estimate developed for change orders?
- How were
change orders negotiated? How were differences between original estimates
and final negotiated amounts justified/documents?
- How were
time and material change orders administered?
- How many
change orders were time and material?
- How long
from change identification to negotiated agreement?
- How was
the owner review/approval process implemented?
- What were
logging/tracking procedures for change orders?
- How
involved was the A/E in the process of change order finalization?
Dispute/Claims Control Checklist
- How were
potential claims identified?
- Were
monetary values for potential claims assigned?
- Were
disputes/claims resolved during the course of construction?
- Were time
extension disputes traced as disputes/claims?
- What was
the process of alerting owner to potential or actual disputes/claims?